Technology Upgrade - Waste heat recovery
F.O
Steam to process
Steam to process
Steam to process
Flue gas at 230 to 270 Deg C
Flue gas at 230 to 270 Deg C
Flue gas at 280 to 300 Deg C
Recover
Waste heat from the flue gases
¥ FG temp can be at 170 Deg C
¥ Hot water may be generated
¥For
use in process
Savings potential:
1.2 million KSh per year (6%)
Investment: 0.6 million KSh
Pay back: 6 months